TotalEnergies' Mozambique gas project at a turning point
Approximately 9,000 new electricity connections will be implemented by 2017 as per the rural electrification project,
which is running in eight districts in Cabo Delgado Province.
The project will oversee the expansion of the electricity network to 28 towns. The implementation of the project includes the construction of 134-kilometres of power transmission lines, 73-kilometres of low voltage lines and 61 kilometres of medium voltage lines, in addition to erecting 48 processing posts.
According to the Provincial Director of Mineral Resources and Energy of Cabo Delgado Province, Ramiro Nguiraze, the government will invest close to US$9- million for the implementation of the project.
Leave a Reply
Be the First to Comment!
You must be logged in to post a comment.
You must be logged in to post a comment.