The Mozambique LNG Project operated by Total E&P Mozambique Area 1 (TEPMA1), and the Government of Mozambique, announce that the Project will progressively resume construction activities at the Afungi site, following the implementation of additional site security measures.
After the security events that occurred in December 2020 near the Mozambique LNG project site and led to the temporary demobilisation of the project workforce, Total and the Government of Mozambique have worked together to define and implement an action plan with the objective of reinforcing, in a sustained manner, the security of the Afungi site and of the surrounding area and neighbouring villages.
The Government of Mozambique has declared the area within a 25 km perimeter surrounding the Mozambique LNG Project as a special security area. A comprehensive roadmap, including the reinforcement of the security infrastructure and the strengthening of the public security forces has been defined and implemented, allowing a gradual remobilisation of the project workforce and the resumption of LNG plant construction activities as well as community development programs carried out by the project.
The control of the special security area around the Afungi site remains ensured exclusively by public security forces assigned by the Mozambican Ministries of Defense and Interior, under a Memorandum of Understanding signed in July 2020 between the Government of Mozambique and TEPMA1. The Government of Mozambique is committed that the personnel assigned to the protection of Mozambique LNG shall act according to the Voluntary Principles on Security and Human Rights (VPSHR) and international human rights standards. The Mozambique LNG Project, which is in charge of the security of the construction site itself, does not use the services of any armed private security providers.
Moreover, Total announces that Mozambique LNG has satisfied all the conditions precedent and complied with all relevant statutory requirements for the first debt drawdown of the project financing signed on 15th July 2020 with eight export credit agencies, 19 commercial banks and the African Development Bank. This first drawdown will take place at the beginning of April 2021.
Total also confirms its objective to deliver Mozambique LNG’s first cargoes in 2024.
Total E&P Mozambique Area 1 Limitada, a wholly owned subsidiary of Total SE, operates Mozambique LNG with a 26.5% participating interest alongside ENH Rovuma Área Um, S.A. (15%), Mitsui E&P Mozambique Area1 Limited (20%), ONGC Videsh Rovuma Limited (10%), Beas Rovuma Energy Mozambique Limited (10%), BPRL Ventures Mozambique B.V. (10%), and PTTEP Mozambique Area 1 Limited (8.5%).
About Mozambique LNG project
Mozambique LNG is the country’s first onshore LNG development. The project includes the development of the Golfinho and Atum fields located within Offshore Area 1 and the construction of a two-trains liquefaction plant with a capacity of 13.12 million tonnes per year.
The Area 1 contains approximately 65 Tcf of gas resources, of which 18 Tcf will be developed with the first two trains. The Final Investment Decision of Mozambique LNG project was announced on June 18, 2019, and the project is expected to come into production by 2024.
About Total Mozambique
Present in Mozambique for nearly 30 years, Total Mozambique is a major player in the downstream petroleum products market – gas stations network, industrial and mining customers, lubricants and logistics. Total has an estimated market share of 14%.
About Total
Total is a broad energy company that produces and markets fuels, natural gas and electricity. Our 100,000 employees are committed to better energy that is more affordable, more reliable, cleaner and accessible to as many people as possible. Active in more than 130 countries, our ambition is to become the responsible energy major.
Leave a Reply
Be the First to Comment!
You must be logged in to post a comment.
You must be logged in to post a comment.