Trans African Concessions (TRAC) takes pride in being the concessionaire of the Maputo Corridor and is committed to keeping the entirety of this international route in pristine condition and on par with world standards.
To ensure the N4 remains safe, efficient, and well-maintained, TRAC continuously undertakes a range of construction projects along the route. These include routine pavement rehabilitation and strengthening, as well as major upgrades such as road widening, interchange construction, and new bridges. In addition to the Schoemanskloof upgrade and rehabilitation project currently underway, TRAC has also commenced four new infrastructure projects along the N4. These are:
* Solomon Mahlangu Drive to Bronkhorspruit (N4-1 km 21 to km 25 & N4-2 km 0 to km 30)
Project Details: Rehabilitation of the N4
Commencement Date: July 2025
Expected Completion Date: July 2027
Progress of completion: 0%
Traffic Accommodation: Shoulder Lane closures to be implemented later Main
Contractor: TauPele Construction
* Van Dijksdrift Interchange to Wonderfontein (N4-4 km 9 to km 47) & N4-5 km 0 to km 10)
Project Details: Rehabilitation of the N4
Commencement Date: July 2025
Expected Completion Date: July 2027
Progress of completion: 0%
Traffic Accommodation: Shoulder Lane closures to be implemented later Main
Contractor: ACTOP Construction
* Schoemanskloof (N4-6Y km 2,7 to km 62)
Project Details: Upgrading and Rehabilitation of Schoemanskloof
Commencement Date: October 2024
Expected Completion Date: October 2027
Progress of completion: 20%
Traffic Accommodation: Shoulder lane closures; Stop/Go closures to be implemented later Main
Contractor: TauPele Construction
* Crocodile Gorge Upgrade (N4-7 km 74.1 to km 90.05)
Project Details: Upgrading and Rehabilitation of Section 10
Commencement Date: March 2025
Expected Completion Date: February 2028
Progress of completion: 7%
Traffic Accommodation: Stop/Go closure
Main Contractor: Raubex Construction
* Hectorspruit to Lebombo Border post (N4-8X km 39 to km 70)
Project Details: Rehabilitation of the N4
Commencement Date: May 2025
Expected Completion Date: May 2027
Progress of completion: 5%
Traffic Accommodation: Shoulder Lane closures; Stop/Go closures to be implemented later Main
Contractor: Roadspan/WBHO JV
* Ressano Garcia Border Post to Moamba Interchange (EN4-1 km 0 to km 41.29)
Project Details: Rehabilitation and the construction of a new passing lane of Section 16
Commencement Date: October 2024
Expected Completion Date: December 2027
Progress of completion: 10%
Traffic Accommodation: Stop/Go closures
Main Contractor: WBHO Projects Mozambique
* Moamba I/C to Tchumene Interchange (EN4-2 km 0 to km 25)
Project Details: The mill and replace of N4 MDC section 17
Commencement Date: June 2025
Expected Completion Date: July 2025
Progress of completion: 5%
Traffic Accommodation: Daytime Stop/Go closures
Main Contractor: TC Projectos LDA
Although TRAC endeavours to prevent traffic disruptions due to road construction, traffic flow may be affected in certain areas, at specific times, and during peak traffic time. Therefore, we urge road users to visit www.tracn4.co.za for regular, real-time updates, follow that will assist them to plan their trips accordingly.